Document scope changes before the work starts. List added or removed work, and the template calculates the change amount and the new revised contract total — with schedule impact and signature lines.
| Change order # | CO-003 |
| Date | 2026-11-04 |
| Project | Kitchen remodel |
| Original contract date | 2026-09-15 |
| Description | Qty | Unit | Amount |
|---|---|---|---|
| Quartz countertop upgrade (42 sq ft), net of laminate credit | 1 | $2,650.00 | $2,650.00 |
| Under-cabinet LED lighting, new 15A circuit | 1 | $780.00 | $780.00 |
| Credit: remove backsplash tile from scope | 1 | $-420.00 | $-420.00 |
Client requested upgrade from laminate to quartz countertops and an added under-cabinet lighting circuit.
Adds 3 working days. New estimated completion: December 12, 2026.
This change order becomes part of the original contract. All other terms remain unchanged. Work on these changes begins after both parties sign.
A change order is a written amendment to a construction or service contract that records changes to scope, price or schedule after the original agreement is signed.
The project and contract reference, a clear description of the change, the cost of the change, the revised contract total, the schedule impact and signatures from both parties.
Yes. Enter removed work as a negative amount (a credit) and the revised contract total goes down.
Yes. Edit online and download a PDF or Excel file with no sign-up.
Clean, professional invoice for freelancers and small businesses.
Bold, modern invoice with color accents.
Track hours and rates for freelance projects.
Invoice for repairs and odd jobs with labor, materials and trip fees.